Hwy. 52 to Close in Both Directions at I-90 Southeast of Rochester Monday Morning
Update: Hwy. 52 will reopen at approximately 2 p.m. on Tuesday, September 29. Crews will resume work at 1 a.m. on Thursday October 1 and keep the road closed until 9 p.m. Thursday. The work was supposed to occur over three consecutive days but the schedule was modified due to forecasted heavy rains Tuesday and Wednesday.
Rochester, MN (KROC-AM News)- Another closure is coming to the I-90 and Hwy. 52 interchange southeast of Rochester.
Closure of Hwy. 52 at I-90 Interchange Starts Monday Morning
The closure was supposed to happen earlier this month, but it was pushed back due to the heavy rainfall that hit southeast Minnesota last weekend.
See Also: DMC Approves $500K in Assistance for Rochester Businesses Impacted by Link BRT Construction
The Minnesota Department of Transportation (MnDOT) says Hwy. 52 will close in both directions at the I-90 interchange starting on Monday.
The recently-completed flyover ramp connecting southbound Hwy. 52 with eastbound I-90 is included in the closure. The offramp from westbound I-90 to northbound Hwy. 52 will remain open, according to MnDOT.

During the closure crews will be removing the temporary bridge work on the I-90 westbound overpass, painting the bridge rails and beams, completing final pavement on northbound and southbound Highway 52, and installing temporary striping.
Detour Route
The southbound Hwy. 52 detour will direct drivers to I-90 via Hwy. 63 in Rochester. From there, they’ll enter westbound I-90 and exit at County Rd. 7, which will take them to Hwy. 52 north of Chatfield.
Northbound Hwy. 52 motorists will be directed to I-90 via County Rd. 7 then exit I-90 at Hwy. 52 exit. I-90 eastbound and westbound drivers seeking southbound Hwy. 52 will be detoured to the County Rd. 7 interchange.
Eastbound I-90 motorists looking for northbound Hwy. 52 can either get to it via Hwy. 63 northbound. The closure is scheduled to start at 1 a.m. on Monday. Hwy. 52 is set to reopen by 9 p.m. on Wednesday.
The $27.5 million project to transform the interchange is in its third and final year.
First Fall Frost Dates for Minnesota in 2026
Gallery Credit: Samm Adams